Below you will find a comprehensive guide to adding work order costs to a work order.
Step-by-Step Guide to Adding Work Order Charges:
1. Open the work order “Cost” section and click “Add Charge.”
2. From here, you will have the ability to choose from a dropdown list of charge types.
3. You can choose from the following charge types:
Labor
A. Charge Type: Select “Labor” to add a labor charge. That will prompt the following fields to populate and the list of “Staff” to populate in the “Maintenance Laborer” dropdown.
B. Maintenance Laborer: The list of “Staff” from your Work Order Configuration section.
C. Description: A description of the labor completed.
D. Billed To: The billable party. This could be the Housing Authority, Tenant, or Other.
E. Date of Work: Date the work was done.
F. Hours: Number of hours, in a decimal format.
G. Maintenance Laborers Hourly Rate: The rate that corresponds with the labor attached to this work order. These rates are also configurable in Work Order Configuration in each staff member’s profile. To add a custom rate, simply select and fill in the “Custom” text field.
H. Calculated Hours and Amount Summary: Here, you can see the breakdown of the hours and minutes as well as how that calculates using the selected “hourly rate.”
I. Cancel or Save: Click the “cancel” button to stop adding the cost or “save” to save the cost to the work order.
Materials
A. Charge Type: Select Material to add a labor charge. That will prompt the following fields to populate and the ability to pull from previously added materials.
B. Description: A description of the material used.
C. Billed To: The billable party. This could be the Housing Authority, Tenant, or Other.
D. Custom Attributes: Populate any custom attributes that populate in this section. In the example above, we have a dropdown for Warehouse.
E. Choose Material: This section is specifically for those who utilize our Inventory feature. By adding materials in Doorways, you can pull them into work orders. If you do not, you’ll just add a custom quantity and price in the section below this one.
F. Quantity and Pricing: Here, your previously selected material will populate with the pre-configured amount for that material. You can add the quantity, the amount, or add a custom amount by selecting the corresponding radio button.
G. Cancel or Save: Click the “cancel” button to stop adding the cost or “save” to save the cost to the work order.
Vendor/Contractor
A. Charge Type: Select Vendor/Contractor to add a labor charge. That will prompt the following fields to populate and the list of Vendors/Contractors to populate in the dropdown.
B. Vendor/Contractor: The list of vendors/Contractors from your Work Order Configuration section.
C. Description: A description of the labor completed.
D. Billed To: The billable party. This could be the Housing Authority, Tenant, or Other.
E. Hours: Number of hours, in a decimal format.
F. Vendors Hourly Rate: The rate that corresponds with the labor attached to this work order. These rates are also configurable in Work Order Configuration in each vendor member’s profile. To add a custom rate, simply select and fill in the “Custom” text field
G. Purchase Order: Input the number associated with the invoice from the vendor/contractor.
H. Calculated Hours and Amount Summary: Here, you can see the breakdown of the hours and minutes as well as how that calculates using the selected “hourly rate.”
I. Cancel or Save – Click the “cancel” button to stop adding the cost or “save” to save the cost to the work order.
Mileage
A. Charge Type: Select “Mileage” to add a mileage charge.
B. Description: A description of the miles traveled/why.
C. Billed To: The billable party. This could be the Housing Authority, Tenant, or Other.
D. Total Mileage: Total number of miles traveled over the entirety of the work order. This can be edited as you go by editing the cost.
E. Cost Per Mile: The cost per mile as allotted by your housing authority or HUD.
F. Total Cost: Total cost (mileage multiplied by the cost per mile).
G. Cancel or Save: Click the “cancel” button to stop adding the cost or “save” to save the cost to the work order.
Other
A. Charge Type: Select “Other” to add a charge that does not fit within the other cost types.
B. Description: A description of the charge.
C. Billed To: The billable party. This could be the Housing Authority, Tenant, or Other.
D. Total Amount: Total amount of the cost.
E. Cancel or Save: Click the “cancel” button to stop adding the cost or “save” to save the cost to the work order.